subject
Business, 19.10.2020 18:01 abecobos37

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2016, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2018. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: At 12-31-2016 At 12-31-2017 At 12-31-2018
Percentage of completion 10% 60% 100%
Costs incurred to date $350,000 $2,500,000 $4,250,000
Estimated costs to complete 3,150,000 1,700,000 0
Billings to Axelrod, to date 720,000 2,170,000 3,600,000
Required:
1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years.
Year Gross Profit (Loss) Recognized
2016
2017
2018
Total project profit (loss)
2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.
Year Gross Profit (Loss) Recognized
2016
2017
2018
3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2016 and 2017 as either cost in excess of billings or billings in excess of costs.
Balance Sheet (Partial) 2016 2017
Current assets:
Current liabilities:

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 11:30
17.     chef a says that garnish should be added to a soup right before serving. chef b says that garnish should be cooked with the other ingredients in a soup. which chef is correct? a. chef a is correct. b. both chefs are correct. c. chef b is correct. d. neither chef is correct. student c   incorrect which is correct answer?
Answers: 2
question
Business, 22.06.2019 16:30
Corrective action must be taken for a project when (a) actual progress to the planned progress shows the progress is ahead of schedule. (b) the technical specifications have been met. (c) the actual cost of the activities is less than the funds received for the work completed. (d) the actual progress is less than the planned progress.
Answers: 2
question
Business, 23.06.2019 01:30
Determine allison's december 31, 2018, investment in mathias balance.
Answers: 2
question
Business, 23.06.2019 09:30
Which of these is true about a mandated reporter
Answers: 1
You know the right answer?
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on J...
Questions
question
Mathematics, 16.11.2022 00:53
Questions on the website: 13722361