APPENDIX TWO Computer Project Exercises In developing the exercises, trade-offs had to be made to enrich the learning experience. One of the major problems students initially encounter is data and detail overload. This reduces their ability to identify project and data problems and to compare alternatives. Although the project found in the exercises is real, it has been reduced and detail has been eliminated many times to concentrate on applying project management principles and understanding linkages. In addition, other simplifying assumptions have been made so that students and instructors can trace problems and discuss outcomes. These assumptions detract from reality, but they keep the focus on the objectives of the exercises and reduce student frustration with software intricacies. Moving from these exercises to real projects is primarily one of increasing detail. The simplifying assumptions are given below (make sure they are included in "default," "preferences," and/or "options" sections of the software used): The POM1 Project Big Kola Company has been concerned that specialized fruit drinks have been eroding their cola market. The CEO mandates that "If you can’t beat them, join them." Grape juice was the first product that was successful after an advertising blitz claiming the antitoxin benefits. Lately, competition is compressing grape juice margins and profits. Months of additional market surveys and focus groups have resulted in three potential high-margin drinks: cranberry, blueberry, and pomegranate. All these choices represent antitoxins. The decision is to produce the pomegranate drink that has many health claims. For example, the relative ability of these juices to eliminate harmful free radicals (antitoxins) is 71 percent for pomegranate, 33 percent for blueberry, and 20 percent for cranberry (Technion Institute of Technology). The market potential appears very attractive and should have a higher profit margin than the other potential juice products. Another appeal for pomegranate juice is its familiarity in the Middle East and Asia. The Priority Matrix for the POM1 Project is: Time Scope Cost Constrain; Constrain = Cost; Enhance = Scope; Accept = Time Connor Gage, the project manager, has formed his project team and the members have come up with the following work breakdown structure. 1.0 POM+1Project 1.1 R&D product development 1.1.1 Need survey 1.1.2 Set product specs 1.1.3 Shelf life report 1.1.4 Nutrition report 1.2 Secure fruit suppliers 1.3 Initial Production 1.3.1 Equipment rehab 1.3.2 Production trials 1.3.3 Quality trials 1.3.4 Quality metrics 1.3.5 Quality training 1.4 Distribution 1.4.1 Market testing 1.4.2 Package design 1.4.3 Select distributors 1.5 Legal 1.5.1 Complete FDA certification 1.5.2 Register trademark 1.6 Prepare product launch Part 1. Develop the WBS outline using the software available (save your file). 2. Use this file and the information provided below to create a project schedule. 3. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26. 4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given off. 5. The project team works eight-hour days, Monday through Friday. 6. The project will begin on January 3, 2012.
7. Based on this schedule, submit a memo that answers the following questions: a. When is the project estimated to be completed?
How many working days will it take?
b. What is the critical path?
c. Which activity has the most total slack?
d. How sensitive is this network?
e. Identify two sensible milestones and explain your choice.
Appendix 2 Computer Project Exercises 627 Include the following (one page) printouts: • A Gantt chart. • A network diagram highlighting the critical path.
• A schedule table reporting ES, LS, EF, LF, and slack for each activity. Hints: Change the timescale to months and weeks. The estimated duration of the project is 135 days. Remember: Save your files for future exercises! The following information has been derived from the WBS. Note that the activity number is what appears in the software with the complete WBS entered. #* Activity Duration Predecessor(s) 3 Need survey 20 None 4 Set product specs 15 3 5 Shelf life report 10 4 6 Nutrition report 5 4 7 Select fruit suppliers 20 5, 6 9 Equipment rehab 30 4 10 Production trials 15 7, 9 11 Quality trials 20 10 12 Quality metrics 5 11 13 Quality training 15 12 15 Market testing 30 5, 6 16 Package design 15 15 17 Select distributors 25 5, 6 19 Complete FDA certification 15 7, 15 20 Register trademark 5 7, 15 21 Prepare product launch 15 13, 16, 17, 19FS + 25 days, 20FS + 15 days

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 21:10
Of the roles commonly found in the development, maintenance, and compliance efforts related to a policy and standards library, which of the following has the responsibilities of directing policies and procedures designed to protect information resources, identifying vulnerabilities, and developing a security awareness program?
Answers: 3
question
Business, 22.06.2019 01:30
Eliminating entries (including goodwill impairment) and worksheets for various years on january 1, 2013, porter company purchased an 80% interest in the capital stock of salem company for$850,000. at that time, salem company had capital stock of $550,000 and retained earnings of $80,000.differences between the fair value and the book value of the identifiable assets of salem company were asfollows: fair value in excess of book valueequipment$130,000land65,000inventory40,000the book values of all other assets and liabilities of salem company were equal to their fair values onjanuary 1, 2013. the equipment had a remaining life of five years on january 1, 2013. the inventory was sold in2013.salem company’s net income and dividends declared in 2013 and 2014 were as follows: year 2013 net income of $100,000; dividends declared of $25,000year 2014 net income of $110,000; dividends declared of $35,000required: a.prepare a computation and allocation schedule for the difference between book value of equity acquired andthe value implied by the purchase price.b.present the eliminating/adjusting entries needed on the consolidated worksheet for the year endeddecember 31, 2013. (it is not necessary to prepare the worksheet.)lo6lo1
Answers: 1
question
Business, 22.06.2019 02:00
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
question
Business, 22.06.2019 04:00
You are thinking of making your mansion more energy efficient by replacing some of the light bulbs with compact fluorescent bulbs, and insulating part or all of your exterior walls. each compact fluorescent light bulb costs $4 and saves you an average of $2 per year in energy costs, and each square foot of wall insulation costs $1 and saves you an average of $0.20 per year in energy costs.† your mansion has 150 light fittings and 3000 sq ft of uninsulated exterior wall. to impress your friends, you would like to spend as much as possible, but save no more than $750 per year in energy costs (you are proud of your large utility bills). how many compact fluorescent light bulbs and how many square feet of insulation should you purchase? how much will you save in energy costs per year? (if an answer does not exist, enter dne.)
Answers: 1
You know the right answer?
APPENDIX TWO Computer Project Exercises In developing the exercises, trade-offs had to be made to en...
Questions
question
Mathematics, 18.08.2019 08:30
question
Mathematics, 18.08.2019 08:30
question
Mathematics, 18.08.2019 08:30
question
Mathematics, 18.08.2019 08:30
Questions on the website: 13722363