If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists? A. Start to Finish
B. Start to Start
C. Finish to Start
D. Finish to Finish
E. Any of these could be correct.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 04:50
Harwood company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. the company's predetermined overhead rate of $2.50 per machine-hour was based on a cost formula that estimates $240,000 of total manufacturing overhead for an estimated activity level of 96,000 machine-hours. required: 1. assume that during the year the company works only 91,000 machine-hours and incurs the following costs in the manufacturing overhead and work in process accounts: compute the amount of overhead cost that would be applied to work in process for the year and make the entry in your t-accounts. 2a. compute the amount of underapplied or overapplied overhead for the year and show the balance in your manufacturing overhead t-account. 2b. prepare a journal entry to close the company's underapplied or overapplied overhead to cost of goods sold.
Answers: 1
question
Business, 22.06.2019 10:30
On july 1, oura corp. made a sale of $ 450,000 to stratus, inc. on account. terms of the sale were 2/10, n/30. stratus makes payment on july 9. oura uses the net method when accounting for sales discounts. ignore cost of goods sold and the reduction of inventory. a. prepare all oura's journal entries. b. what net sales does oura report?
Answers: 2
question
Business, 22.06.2019 10:40
Two assets have the following expected returns and standard deviations when the risk-free rate is 5%: asset a e(ra) = 18.5% σa = 20% asset b e(rb) = 15% σb = 27% an investor with a risk aversion of a = 3 would find that on a risk-return basis. a. only asset a is acceptable b. only asset b is acceptable c. neither asset a nor asset b is acceptable d. both asset a and asset b are acceptable
Answers: 2
question
Business, 22.06.2019 16:20
The assumptions of the production order quantity model are met in a situation where annual demand is 3650 units, setup cost is $50, holding cost is $12 per unit per year, the daily demand rate is 10 and the daily production rate is 100. the production order quantity for this problem is approximately:
Answers: 1
You know the right answer?
If testing cannot be completed any earlier than four days after the prototype has been built, what t...
Questions
Questions on the website: 13722359