The following shows seven tasks required for a project, task times, and the precedence relationships among tasks. Construct Gantt chart and determine the project completion time.
Activity Time (weeks) Predecessors
А 3 None
B 2 None
C 4 A
D 5 A
E 2 B, D
F 4 B
G 5 С, Е,Р
Answers: 3
Business, 22.06.2019 22:10
jackie's snacks sells fudge, caramels, and popcorn. it sold 12,000 units last year. popcorn outsold fudge by a margin of 2 to 1. sales of caramels were the same as sales of popcorn. fixed costs for jackie's snacks are $14,000. additional information follows: product unit sales prices unit variable cost fudge $5.00 $4.00 caramels $8.00 $5.00 popcorn $6.00 $4.50 the breakeven sales volume in units for jackie's snacks is
Answers: 1
Business, 22.06.2019 23:30
Shelby bought her dream car, a 1966 red convertible mustang, with a loan from her credit union. if shelby paid 5.1% and the bank earned a real rate of return of 3.5%, what was the inflation rate over the life of the loan?
Answers: 2
Business, 23.06.2019 03:00
The following information is needed to reconcile the cash balance for gourmet catering services.* a deposit of $5,600 is in transit.* outstanding checks total $1,000.* the book balance is $6,400 at february 28, 2019.* the bookkeeper recorded a $1,800 check as $17,200 in payment of the current month's rent.* the bank balance at february 28, 2019 was $17,410.* a deposit of $400 was credited by the bank for $4,000.* a customer's check for $3,300 was returned for nonsufficient funds.* the bank service charge is $90.what was the adjusted book balance?
Answers: 1
The following shows seven tasks required for a project, task times, and the precedence relationships...
Chemistry, 28.10.2020 14:00
Mathematics, 28.10.2020 14:00
Physics, 28.10.2020 14:00
Mathematics, 28.10.2020 14:00
History, 28.10.2020 14:00
Social Studies, 28.10.2020 14:00
Physics, 28.10.2020 14:00
Biology, 28.10.2020 14:00
English, 28.10.2020 14:00
Mathematics, 28.10.2020 14:00
German, 28.10.2020 14:00
History, 28.10.2020 14:00