A subcontractor is responsible for outfitting six satellites that will be used for solar research. Four of the six have been completed in a total of 600 hours. If the crew has a 75% learning curve, how long should it take them to finish the last two units?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 00:30
Aprice ceiling is “binding” if the price ceiling is set below the equilibrium price. suppose that the equilibrium price is $5. if a price ceiling is set at $6, this will not affect the market in any way since $5 remains a legally allowable price (since $5 < $6). a price ceiling of $6 is called a “non-binding” price ceiling. on the other hand, if the price ceiling is set at $4, the price ceiling is “binding” because the natural equilibrium price is $5 but that is no longer allowed. what happens when there is a binding price ceiling? at a price below the equilibrium price, quantity demanded exceeds quantity supplied. there is a shortage. normally, price increases eliminate shortages by increasing quantity supplied and decreasing quantity demanded. in this case, however, price increases are not allowed past the price ceiling. we therefore predict that the observed market price will be right at the price ceiling and there will be a permanent shortage. the observed quantity bought and sold will be dictated by the quantity supplied at the price ceiling. although consumers would like to buy more, there are no more units for sale
Answers: 1
question
Business, 22.06.2019 02:00
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
question
Business, 22.06.2019 05:50
Acompany that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts. prior to buying the new equipment, the company used 6 workers, who produced an average of 79 carts per hour. workers receive $16 per hour, and machine coast was $49 per hour. with the new equipment, it was possible to transfer one of the workers to another department, and equipment cost increased by $11 per hour while output increased by four carts per hour. a) compute the multifactor productivity (mfp) (labor plus equipment) under the prior to buying the new equipment. the mfp (carts/$) = (round to 4 decimal places). b) compute the productivity changes between the prior to and after buying the new equipment. the productivity growth = % (round to 2 decimal places)
Answers: 3
question
Business, 22.06.2019 16:00
Which plan offers a tax-free education?
Answers: 1
You know the right answer?
A subcontractor is responsible for outfitting six satellites that will be used for solar research. F...