A store has 5 years remaining on its lease in a mall. Rent is $1,900 per month, 60 payments remain, and the next payment is due in 1 month. The mall's owner plans to sell the property in a year and wants rent at that time to be high so that the property will appear more valuable. Therefore, the store has been offered a "great deal" (owner's words) on a new 5-year lease. The new lease calls for no rent for 9 months, then payments of $2,600 per month for the next 51 months. The lease cannot be broken, and the store's WACC is 12% (or 1% per month). A. Should the new lease be accepted? (Hint: Be sure to use 1% per month.)

B. If the store owner decided to bargain with the mall's owner over the new lease payment, what new lease payment would make the store owner indifferent between the new and the old leases?

C. The store owner is not sure of the 12% WACC. It could be higher or lower. At what nominal WACC would the store owner be indifferent between the two leases?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:40
Alocal club is selling christmas trees and deciding how many to stock for the month of december. if demand is normally distributed with a mean of 100 and standard deviation of 20, trees have no salvage value at the end of the month, trees cost $20, and trees sell for $50 what is the service level?
Answers: 2
question
Business, 22.06.2019 08:00
Suppose the number of equipment sales and service contracts that a store sold during the last six (6) months for treadmills and exercise bikes was as follows: treadmill exercise bike total sold 185 123 service contracts 67 55 the store can only sell a service contract on a new piece of equipment. of the 185 treadmills sold, 67 included a service contract and 118 did not.
Answers: 1
question
Business, 22.06.2019 10:30
The card shoppe needs to maintain 21 percent of its sales in net working capital. currently, the store is considering a four-year project that will increase sales from its current level of $349,000 to $408,000 the first year and to $414,000 a year for the following three years of the project. what amount should be included in the project analysis for net working capital in year 4 of the project?
Answers: 3
question
Business, 22.06.2019 16:30
On april 1, the cash account balance was $46,220. during april, cash receipts totaled $248,600 and the april 30 balance was $56,770. determine the cash payments made during april.
Answers: 1
You know the right answer?
A store has 5 years remaining on its lease in a mall. Rent is $1,900 per month, 60 payments remain,...
Questions
question
Mathematics, 26.01.2020 17:31
question
Mathematics, 26.01.2020 17:31
Questions on the website: 13722367