Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:a 6.0 -b 7.2 -c 5.0 ad 6.0 b, ce 4.5 b, cf 7.7 dg 4.0 e, fa) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length?d) Draw a Gantt chart for the project.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 18:40
Reactive power generation has the following capital structure. its corporate tax rate is 40%. security market value required rate of return debt $ 30 million 4 % preferred stock 30 million 6 common stock 40 million 10 what is its wacc? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places.)
Answers: 2
question
Business, 21.06.2019 21:20
Reqwest llc agrees to sell one hundred servers to social media networks, inc. the servers, which social media networks expressly requires to have certain amounts of memory, are to be shipped “f.o.b. social media networks distribution center in tampa, fl.” when the servers arrive, social media networks rejects them and informs reqwest, claiming that the servers do not conform to social media networks’ memory requirement. a few hours later, the servers are destroyed in a fire at social media networks’ distribution center. will reqwest succeed in a suit against social media networks for the cost of the goods?
Answers: 3
question
Business, 22.06.2019 11:00
Your debit card is stolen, and you report it to your bank within two business days. how much money can you lose at most? a. $500 b. $25 c. $50 d. $150
Answers: 2
question
Business, 22.06.2019 12:30
M. cotteleer electronics supplies microcomputer circuitry to a company that incorporates microprocessors into refrigerators and other home appliances. one of the components has an annual demand of 235 units, and this is constant throughout the year. carrying cost is estimated to be $1.25 per unit per year, and the ordering (setup) cost is $21 per order. a) to minimize cost, how many units should be ordered each time an order is placed? b) how many orders per year are needed with the optimal policy? c) what is the average inventory if costs are minimized? d) suppose that the ordering cost is not $21, and cotteleer has been ordering 125 units each time an order is placed. for this order policy (of q = 125) to be optimal, determine what the ordering cost would have to be.
Answers: 1
You know the right answer?
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois,...
Questions
question
Mathematics, 09.10.2021 14:00
question
Mathematics, 09.10.2021 14:00
question
Mathematics, 09.10.2021 14:00
question
History, 09.10.2021 14:00
question
Business, 09.10.2021 14:00
question
Mathematics, 09.10.2021 14:00
Questions on the website: 13722367