Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20
2 - 3 2 60 60
3 1 4 0 70 0
4 1 2 1 50 10
5 2 5 3 100 60
6 3 2 1 90 100
7 4 5 1 50 30
8 5 2 0 60 40
9 6,7,8 3 1 200 200
Consider the project above. If the indirect costs of the project are: $90 at 15 days, $75 at 14 days, $50 at 13 days, $40 at 12 days, and $30 at 11 days.
Please help crash this project in a manner that minimizes the sum of the total direct and indirect costs.
What is the current estimated project duration in days without any crashing?
A. 11
B. 14
C. 13
D. 15

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 18:40
Under t, the point (0,2) gets mapped to (3,0). t-1 (x,y) β†’
Answers: 3
question
Business, 22.06.2019 21:10
Kinc. has provided the following data for the month of may: inventories: beginning ending work in process $ 17,000 $ 12,000 finished goods $ 46,000 $ 50,000 additional information: direct materials $ 57,000 direct labor cost $ 87,000 manufacturing overhead cost incurred $ 63,000 manufacturing overhead cost applied to work in process $ 61,000 any underapplied or overapplied manufacturing overhead is closed out to cost of goods sold. the adjusted cost of goods sold that appears on the income statement for may is:
Answers: 3
question
Business, 22.06.2019 22:00
The following table gives the map coordinates and the shipping loads for a set of cities that we wish to connect through a central hub.,(7,(4,(7,(6,(2,( 2,) for the location of the proposed new central hub, the coordinates should be near: x==) if the shipments from city a double, for the location of the proposed new central hub, the coordinates should be near: x==.926.865.017.21
Answers: 1
question
Business, 23.06.2019 00:30
Industrial engineers who specialize in ergonomics are concerned with designing workspace and devices operated by workers so as to achieve high productivity and comfort. a paper published in this research area reports on a study of preferred height for an experimental keyboard with large forearm-wrist support. a sample of 31 trained typists resulted in an average preferred height of 80.0 cm
Answers: 1
You know the right answer?
Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20
Questions
question
Mathematics, 20.09.2020 19:01
Questions on the website: 13722363