A project manager is faced with the following activities and times associated with a building construction for a cancer research facility. Each activity can be crashed at most by 2 weeks. The cost associated with each week time reduction is given below. (note: The 1st crash and 2nd crash costs are associated with the first and second time that a specific activity is crashed. So, if you crash Activity A once, the cost is $9,000, if you have to crash Activity A a second time, the cost is $9,500) Crash Costs
Activity Immediate Normal Time (weeks) 1st crash 2nd crash
Predecessor
A 3 $9,000 $9,500
B A 6 $3,500 $6,000
C А 7 $4,000 $5,000
D B 7 $4,500 $6,000
E C 5 $7,000 $7,500
F D. E 8 $10,000 $12,000
G F 2 $14,000 $16,000
What is the minimum cost to crash this project by 2 weeks?
a. $12,000
b. $9,000
c. $16,000
d. $3,500

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 18:30
Amanufacturer has paid an engineering firm $200,000 to design a new plant, and it will cost another $2 million to build the plant. in the meantime, however, the manufacturer has learned of a foreign company that offers to build an equivalent plant for $2,100,000. what should the manufacturer do?
Answers: 1
question
Business, 22.06.2019 20:00
Richard is one of the leading college basketball players in the state of florida. he also maintains a good academic record. looking at his talent and potential, furman university offers to bear the expenses for his college education.
Answers: 3
question
Business, 22.06.2019 21:00
Noah met an old friend at a coffee shop. he jotted down the friend's new phone number, but later that afternoon he could not find it or remember what he had done with it. a couple of days later, noah went back to the coffee shop, and while waiting in line, he suddenly remembered where he had put the phone number. this is an example of:
Answers: 1
question
Business, 22.06.2019 21:50
Varto company has 9,400 units of its sole product in inventory that it produced last year at a cost of $23 each. this year’s model is superior to last year’s, and the 9,400 units cannot be sold at last year’s regular selling price of $42 each. varto has two alternatives for these items: (1) they can be sold to a wholesaler for $8 each, or (2) they can be reworked at a cost of $251,100 and then sold for $34 each. prepare an analysis to determine whether varto should sell the products as is or rework them and then sell them.
Answers: 2
You know the right answer?
A project manager is faced with the following activities and times associated with a building constr...
Questions
question
Mathematics, 20.03.2021 03:10
question
Mathematics, 20.03.2021 03:20
question
Mathematics, 20.03.2021 03:20
Questions on the website: 13722363