Business, 14.06.2020 02:57 tariqobrien6241

A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 01:30
Suppose the following items were taken from the balance sheet of nike, inc. (all dollars are in millions.) 1. cash $ 2,316.7 7. inventory $ 2,245.6 2. accounts receivable 2,786.2 8. income taxes payable 80.3 3. common stock 2,841.1 9. equipment 1,783.8 4. notes payable 291.2 10. retained earnings 6,162.5 5. buildings 3,959.7 11. accounts payable 2,624.6 6. mortgage payable 1,092.3 perform each of the following. classify each of these items as an asset, liability, or stockholders’ equity, and determine the total dollar amount for each classification. (enter amounts in millions up to 1 decimal place, e.g. 45.5 million.) cash accounts receivable common stock notes payable buildings mortgage payable inventory income taxes payable equipment retained earnings accounts payable assets $ 13092 liability $ 4088.4 stockholders’ equity $ 9003.6 etextbook and media determine nike’s accounting equation by calculating the value of total assets, total liabilities, and total stockholders’ equity. (enter amounts in millions up to 1 decimal place, e.g. 45.5 million.) total assets = total liabilities + total stockholders’ equity
Answers: 3
question
Business, 22.06.2019 14:30
Bridge building company estimates that it will incur $1,200,000 in overhead costs for the year. additionally, the company estimates 50,000 direct labor hours will be spent building custom walking bridges for the year at a total direct labor cost of $600,000. what is the predetermined overhead rate for bridge building company if direct labor costs are to be used as an allocation base?
Answers: 3
question
Business, 22.06.2019 19:30
Nextdoor is an instant messaging application for smartphones. new smartphone users find it easier to connect with friends and relatives through this mobile app when compared to other similar instant messaging applications. hence, it has the largest user base in the industry. thus, nextdoor app's value has increased primarily due to itsa. learning curve effects. b. economies of scale. c. economies of scope. d. network effects.
Answers: 2
question
Business, 22.06.2019 21:40
Western electric has 32,000 shares of common stock outstanding at a price per share of $79 and a rate of return of 13.00 percent. the firm has 7,300 shares of 7.80 percent preferred stock outstanding at a price of $95.00 per share. the preferred stock has a par value of $100. the outstanding debt has a total face value of $404,000 and currently sells for 111 percent of face. the yield to maturity on the debt is 8.08 percent. what is the firm's weighted average cost of capital if the tax rate is 39 percent?
Answers: 2
You know the right answer?
A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start o...
Questions
question
Mathematics, 29.01.2020 12:56
Questions on the website: 13722366