subject
Business, 07.05.2020 06:59 julie1624

You are a project manager for the construction of a 16-mile road. The work is uniformly distributed over 12 weeks. The total approved budget for this project is $600,000. At the end of the first 4 weeks of work, $125,000 has been spent and four miles of road have been completed. The Earned Value at the end of week 4 is: a. $125,000 b. $2,400,000 [$600,000 * 4 miles] c. $150,000 [$600,000 * (4 miles/16 miles)] d. $200,000 [$600,000 * (4 weeks/12 weeks)]

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 01:40
At the local level, the main role of ctsos is to encourage students to become urge them to programs and competitive events. 1. a.interns b.trainees c.members 2. a.participate b.train c.win
Answers: 2
question
Business, 22.06.2019 10:10
Rats that received electric shocks were unlikely to develop ulcers if the
Answers: 1
question
Business, 22.06.2019 11:30
17.     chef a says that garnish should be added to a soup right before serving. chef b says that garnish should be cooked with the other ingredients in a soup. which chef is correct? a. chef a is correct. b. both chefs are correct. c. chef b is correct. d. neither chef is correct. student c   incorrect which is correct answer?
Answers: 2
question
Business, 22.06.2019 13:30
What do you recommend adam do to increase production in a business setting that does not seem to value high productivity?
Answers: 3
You know the right answer?
You are a project manager for the construction of a 16-mile road. The work is uniformly distributed...
Questions
question
Mathematics, 01.09.2019 07:30
question
Computers and Technology, 01.09.2019 07:30
Questions on the website: 13722361