Your project to obtain charitable donations is now 42 days into a planned 52-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 37 days of the project and to bring in $25,800. Even though we are 42 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to run for 42 days starting on day 5 and extending through day 47. We estimate that even though we should have (37/42) 88% of this activity complete, it is actually only 55% complete. This part of the project was scheduled to bring in $150,800 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $51,600. So far $179,000 has actually been brought in on the project.

Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.)

Find the following:

Schedule Variance ($) =

Scheudle Performance Index =

Cost Variance ($) =

Coster Performance Index =

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 07:00
For the past six years, the price of slippery rock stock has been increasing at a rate of 8.21 percent a year. currently, the stock is priced at $43.40 a share and has a required return of 11.65 percent. what is the dividend yield? 3.20 percent 2.75 percent 3.69 percent
Answers: 3
question
Business, 22.06.2019 13:40
After much consideration, you have chosen cancun over ft. lauderdale as your spring break destination this year. however, spring break is still months away, and you may reverse this decision. which of the following events would prompt you to reverse this decision? a. the marginal cost of going to cancun decreases.b. the marginal cost of going to ft. lauderdale decreases.c. the marginal benefit of going to cancun increases.d. the marginal benefit of going to ft. lauderdale decreases.
Answers: 2
question
Business, 22.06.2019 16:50
Atrough in the business cycle occurs when
Answers: 1
question
Business, 22.06.2019 20:00
During the month of march 2017, weimar world, a tax-preparation service, had the following transactions. * billed $496,000 in revenues on credit * received $164,000 from customers' accounts receivable * incurred expenses of $194,000 but only paid $87,700 cash for these expenses * prepaid $32,220 for computer services to be used next month what was the company's accrual basis net income for the month? select one: a. $302,000 b. $264,080 c. $ 41,860 d. $408,300 e. none of the above
Answers: 3
You know the right answer?
Your project to obtain charitable donations is now 42 days into a planned 52-day project. The projec...
Questions
question
Chemistry, 31.03.2020 23:22
question
Spanish, 31.03.2020 23:22
question
Spanish, 31.03.2020 23:22
question
Mathematics, 31.03.2020 23:22
question
Mathematics, 31.03.2020 23:22
Questions on the website: 13722367