A manufacturing company preparing to build a new plant is considering three potential locations for it. The fixed and variable costs for the three alternative locations are presented below.

a. complete a numeric locational cost-volume analysis

b. Indicate over what range each of the alternatives A, B, C is the low-cost choice

c. Is any alternative never perferred? Explain

Cost A B C

Fixed ($) 2,500,000 2,000,000 3,500,000

Vaiable ($ per unit) 21 25 15

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:50
Jen left a job paying $75,000 per year to start her own florist shop in a building she owns. the market value of the building is $120,000. she pays $35,000 per year for flowers and other supplies, and has a bank account that pays 5 percent interest. what is the economic cost of jen's business?
Answers: 3
question
Business, 22.06.2019 16:30
Summarize the specific methods used by interest groups in order to influence governmental decisions making in all three branches of government. provide at least two examples from each branch.
Answers: 3
question
Business, 22.06.2019 20:00
Experienced problem solvers always consider both the value and units of their answer to a problem. why?
Answers: 3
question
Business, 22.06.2019 21:20
Label each of the following statements true, false, or uncertain. explain your choice carefully. a. workers benefit equally from the process of creative destruction. b. in the past two decades, the real wages of low-skill u.s. workers have declined relative to the real wages of high-skill workers. c. technological progress leads to a decrease in employment if, and only if, the increase in output is smaller than the increase in productivity. d. the apparent decrease in the natural rate of unemployment in the united states in the second-half of the 1990s can be explained by the fact that productivity growth was unexpectedly high during that period.
Answers: 3
You know the right answer?
A manufacturing company preparing to build a new plant is considering three potential locations for...
Questions
question
Mathematics, 14.10.2019 14:30
question
Mathematics, 14.10.2019 14:30
question
Biology, 14.10.2019 14:30
question
Biology, 14.10.2019 14:30
Questions on the website: 13722367