You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path. As you have a large budget for the project, you are considering crashing activity A2, which has the potential to shorten the time of A2 by 3 days What do you think about this opportunity?
a. A sood idea, it will reduce the rojet duation by 3 days
b. A bad idea, as A2 is not on the critical path
Answers: 3
Business, 21.06.2019 13:00
The local electronics store is offering a promotion "1-year: same as cash," meaning that you can buy a tv now, and wait a year to pay (with no in
Answers: 1
Business, 21.06.2019 14:10
Needs 83,000 optical switches next year (assume same relevant range). by outsourcing them, worldsystems can use its idle facilities to manufacture another product that will contribute $ 140,000 to operating income, but none of the fixed costs will be avoidable. should worldsystems make or buy the switches? show your analysis.
Answers: 3
Business, 21.06.2019 18:50
Which of the following is not a potential problem with beta and its estimation? sometimes, during a period when the company is undergoing a change such as toward more leverage or riskier assets, the calculated beta will be drastically different than the "true" or "expected future" beta. the beta of "the market," can change over time, sometimes drastically.
Answers: 3
Business, 22.06.2019 10:00
You are president of a large corporation. at a typical monthly meeting, each of your vice presidents gives standard area reports. in the past, these reports have been good, and the vps seem satisfied about their work. based on situational approach to leadership, which leadership style should you exhibit at the next meeting?
Answers: 2
You manage a project with 10 activities. Activities A1, A3, A5, A9 form the critical path. As you ha...
Mathematics, 20.02.2020 01:39
Mathematics, 20.02.2020 01:39
Computers and Technology, 20.02.2020 01:39