You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Question: Do you expect to receive a bonus or penalty? How much do you expect to be given a bonus or penalty?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 20:30
1. gdp is calculated by summing consumption, investment, and exports of all final goods and services produced within the borders of a given country during a specific period the dollar value of all final goods and services produced within the borders of a given country during a specific period government expenditures within the borders of a given country during a specific period the quantity of all final goods and services produced within the borders of a given country during a specific period
Answers: 3
question
Business, 22.06.2019 01:00
Which type of data is generally stored in different file formats, such as text files, spreadsheets, and so on?
Answers: 3
question
Business, 22.06.2019 14:00
Which of the following would not generally be a motive for a firm to hold inventories? a. to decouple or separate parts of the production process b. to provide a stock of goods that will provide a selection for customers c. to take advantage of quantity discounts d. to minimize holding costs e. all of the above are functions of inventory.
Answers: 1
question
Business, 22.06.2019 19:10
Imagine us is a startup that offers high definition 3d prenatal ultrasounds for high-end customers. the service process includes four activities that are conducted in the sequence described below. (the time required for each activity is shown in parentheses): activity 1: welcome a patient and explain the procedure. (20 minutes)activity 2: prep the patient (e.g., show them to the room, apply ultrasound gel). (17 minutes) (*your id number represents the amount of time needed to complete this task)activity 3: take images. (5 minutes)activity 4: discuss diagnostic with patient. (20 minutes)at each location there are employees (servers) s1, s2, and s3. the assignment of tasks to servers is the following: s1 does activities 1 and 2.s2 does activity 3.s3 does activity 4.a. what is the capacity of this process (in customers per hour)? b. suppose 3 patients arrive every hour on average. ignoring any “start of day” or “end of day” effects, what are the utilizations of all three servers (%)? c. suppose each activity can be done by any server and any server can do any set of activities. however, each activity is done by only one server. for example, a possible assignment includes: s1 does activity 1, s2 does activity 2, and s3 does activities 3 and 4. of course, the original assignment of servers to activities is also feasible. what is the maximum capacity of the process (in customers per hour)? d. now consider the capacity measures in (c) and (a), what is the percentage change? why can you improve capacity without using additional resources? (there is no free lunch, right? )note: for all hw assignments, show your process of getting the results. only providing the final answers is not acceptable and will get 0%. if necessary, use a separate sheet of paper to show your work.
Answers: 3
You know the right answer?
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for com...
Questions
question
Physics, 15.11.2020 22:50
question
Biology, 15.11.2020 22:50
question
Mathematics, 15.11.2020 22:50
question
Physics, 15.11.2020 22:50
Questions on the website: 13722363