Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.

PV = $23,000EV = $20,000AC = $25,000BAC = $120,000What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 22:30
Quantitative problem: you need $20,000 to purchase a used car. your wealthy uncle is willing to lend you the money as an amortized loan. he would like you to make annual payments for 4 years, with the first payment to be made one year from today. he requires a 8% annual return. what will be your annual loan payments? round your answer to the nearest cent. do not round intermediate calculations. $ how much of your first payment will be applied to interest and to principal repayment? round your answer to the nearest cent. do not round intermediate calculations. interest: $ principal repayment
Answers: 1
question
Business, 22.06.2019 02:30
Luc do purchased stocks for $6,000. he paid $4,000 in cash and borrowed $2,000 from the brokerage firm. he bought 100 shares at $60.00 per share ($6,000 total). the loan has an annual interest rate of 8 percent. six months later, luc do sold the stock for $65 per share. he paid a commission of $120 and repaid the loan. his net profit was how much? pls
Answers: 3
question
Business, 22.06.2019 12:40
Kumar consulting operates several stock investment portfolios that are used by firms for investment of pension plan assets. last year, one portfolio had a realized return of 12.6 percent and a beta coefficient of 1.15. the average t-bond rate was 7 percent and the realized rate of return on the s& p 500 was 12 percent. what was the portfolio's alpha?
Answers: 1
question
Business, 22.06.2019 15:00
Because gloria's immediate concern was the perceived gender discrimination, she would be more concerned about than intent, resultsresults, intentstatistics, trendsrace,gendergender,race
Answers: 2
You know the right answer?
Given the following information for a one-year project, answer the following questions. Recall that...
Questions
question
Physics, 06.03.2020 23:02
question
Mathematics, 06.03.2020 23:02
question
Mathematics, 06.03.2020 23:02
question
Mathematics, 06.03.2020 23:02
question
Mathematics, 06.03.2020 23:02
Questions on the website: 13722363