Problem 11-21 Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are follows: Week Customer Order 1 52 2 35 3 20 4 12 Use a production lot size of 75 units and no beginning inventory. (Leave no cells blank - be certain to enter "0" wherever required.) June July 1 2 3 4 5 6 7 8 Forecast 50 50 50 50 50 50 50 50 Customer Orders 52 35 20 12 0 0 0 0 Projected on-hand inventory 23 23 Correct 48 48 Correct 73 73 Correct 23 23 Correct 48 48 Correct 73 73 Correct 23 23 Correct 48 48 Correct MPS 75 75 Correct 75 75 Correct 75 75 Correct 0 0 Correct 75 75 Correct 75 75 Correct 0 0 Correct 75
Answers: 2
Business, 21.06.2019 23:00
What is overdraft protection (odp)? a.) a cheap and easy way to always avoid overdrawing a bank account b.) a service to automatically transfer available funds from a linked account to cover purchases, prevent returned checks and declined items when you don’t have enough money in your checking account at the time of the transaction. c.) an insurance policy sold by banks to prevent others from withdrawing your money d.) a service provided by the government that insures individuals bank deposits up to $250,000
Answers: 2
Business, 21.06.2019 23:30
Actual usage for the year by the marketing department was 70,000 copies and by the operations department was 330,000 copies. if a dual-rate cost-allocation method is used, what amount of copying facility costs will be budgeted for the operations department?
Answers: 2
Business, 22.06.2019 01:20
All of the industries and businesses in the country of marksenia are privately owned and sell products at different prices that are not controlled by the government or any other organizational body. consumers in marksenia are free to buy as much of the products as they like from the businesses they want. the country of marksenia has a
Answers: 1
Problem 11-21 Prepare a master schedule given this information: The forecast for each week of an eig...
Social Studies, 17.10.2019 21:50
Mathematics, 17.10.2019 21:50
Mathematics, 17.10.2019 21:50
Mathematics, 17.10.2019 21:50
Mathematics, 17.10.2019 21:50
History, 17.10.2019 21:50
Biology, 17.10.2019 21:50
Biology, 17.10.2019 21:50
Social Studies, 17.10.2019 21:50
Mathematics, 17.10.2019 21:50