A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:30
Mr. smith recently faced a choice between being (a) an economics profes-sor, which pays $60,000/yr, or (b) a safari leader, which pays $50,000/yr. after careful deliberation, smith took the safari job, but it was a close call. "for a dollar more," he said, "i'd have gone the other way."now smith's brother-in-law approaches him with a business proposition. the terms are as follows: - smith must resign his safari job to work full-time in his brother-in-law's business.- smith must give his brother-in-law an interest-free loan of $100,000, which will be repaid in full if and when smith leaves the business. (smith currently has much more than $100,000 in the the business will pay smith a salary of $70,000/yr. he will receive no other payment from the business.the interest rate is 10 percent per year. apart from salary considerations, smith feels that working in the business would be just as enjoyable as being an economics professor. for simplicity, assume there is no uncertainty regarding either smith's salary in the proposed business or the security of his monetary investment in it. should smith join his brother-in-law and, if so, how small would smith's salary from the business have to be to make it not worthwhile for him to join? if not, how large would smith's salary from the business have to be to make it worthwhile for him to join?
Answers: 1
question
Business, 22.06.2019 11:10
How much are you willing to pay for a zero that matures in 10 years, has a face value of $1,000 and your required rate of return is 7%? round to the nearest cent. do not include a dollar sign in your answer. (i.e. if your answer is $432.51, then type 432.51 without $ sign)
Answers: 1
question
Business, 22.06.2019 20:30
The former chairman of the federal reserve, alan greenspan, used the term "irrational exuberance" in 1996 to describe the high levels of optimism among stock market investors at the time. stock market indexes such as the s& p composite price index were at an all-time high. some commentators believed that the fed should intervene to slow the expansion of the economy. why would central banks want to clamp down when the economy is growing? a. to block the formation of unsustainable speculative asset bubbles. b. to curtail excessive profits in the banking system. c. to prevent inflationary forces from gathering momentum. d. all of the above. e. a and c only.
Answers: 3
question
Business, 22.06.2019 20:40
If the ceo of a large, diversified, firm were filling out a fitness report on a division manager (i.e., "grading" the manager), which of the following situations would be likely to cause the manager to receive a better grade? in all cases, assume that other things are held constant.a. the division's basic earning power ratio is above the average of other firms in its industry.b. the division's total assets turnover ratio is below the average for other firms in its industry.c. the division's debt ratio is above the average for other firms in the industry.d. the division's inventory turnover is 6, whereas the average for its competitors is 8.e. the division's dso (days' sales outstanding) is 40, whereas the average for its competitors is 30.
Answers: 1
You know the right answer?
A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000....
Questions
question
Biology, 24.09.2021 03:40
question
Mathematics, 24.09.2021 03:40
Questions on the website: 13722367