Business, 12.03.2020 01:32 yanmanuel2215

A certain project has ten activities. Two activities each have a total slack of 5 days. The total duration of the project’s critical path is 40 days. The duration of the project is .

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 14:00
How many months does the federal budget usually take to prepare
Answers: 1
question
Business, 22.06.2019 14:10
Carey company is borrowing $225,000 for one year at 9.5 percent from second intrastate bank. the bank requires a 15 percent compensating balance. the principal refers to funds the firm can effectively utilize (amount borrowed − compensating balance). a. what is the effective rate of interest? (use a 360-day year. input your answer as a percent rounded to 2 decimal places.) b. what would the effective rate be if carey were required to make 12 equal monthly payments to retire the loan?
Answers: 1
question
Business, 22.06.2019 22:00
Suppose that a paving company produces paved parking spaces (q) using a fixed quantity of land (t) and variable quantities of cement (c) and labor (l). the firm is currently paving 1,000 parking spaces. the firm's cost of cement is $3 comma 600.003,600.00 per acre covered (c) and its cost of labor is $35.0035.00/hour (w). for the quantities of c and l that the firm has chosen, mp subscript upper c baseline equals 60mpc=60 and mp subscript upper l baseline equals 7mpl=7. is this firm minimizing its cost of producing parking spaces?
Answers: 3
question
Business, 23.06.2019 02:00
Acompany sells garden hoses and uses the perpetual inventory system to account for its merchandise. the beginning balance of the inventory and its transactions during september were as follows:
Answers: 2
You know the right answer?
A certain project has ten activities. Two activities each have a total slack of 5 days. The total du...
Questions
question
Social Studies, 09.12.2021 01:00
question
Biology, 09.12.2021 01:00
Questions on the website: 13722363