Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

Activity/Time(weeks)

A:6weeks
B:7 weeks
C:3weeks
D:2weeks
E:4weeks
F:6weeks
G:10weeks
H:7weeks

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 05:10
Responsible for setting the goals and planning for the future as well as leading and controlling the work of others. out the decisions of top management. often responsible for various departments such as the production, marketing, and accounting departments. process or function of planning organizing leading and controlling. the resources arranged in an orderly and functional way to accomplish goals and objectives. the company on track and making sure goals are met. for the daily operations of a business. examples of this are supervisors, office managers, and crew leaders. act or process of creating goals and objectives as well as the strategies to meet them. for the daily operations of a business. examples of this are supervisors, office managers, and crew leaders. how the firm is structured and who is in charge of whom. direction and vision
Answers: 3
question
Business, 22.06.2019 05:30
Laurelton heating & cooling installs and services commercial heating and cooling systems. laurelton uses job costing to calculate the cost of its jobs. overhead is allocated to each job based on the number of direct labor hours spent on that job. at the beginning of the current year, laurelton estimated that its overhead for the coming year would be $ 61 comma 500. it also anticipated using 4 comma 100 direct labor hours for the year. in april comma laurelton started and completed the following two jobs: (click the icon to view the jobs.) laurelton paid a $ 20-per-hour wage rate to the employees who worked on these two jobs. read the requirements requirement 1. what is laurelton's predetermined overhead rate based on direct labor hours? determine the formula to calculate laurelton's predetermined overhead rate based on direct labor hours, then calculate the rate. / = predetermined overhead rate
Answers: 2
question
Business, 22.06.2019 10:30
Trecek corporation incurs research and development costs of $625,000 in 2017, 30 percent of which relate to development activities subsequent to ias 38 criteria having been met that indicate an intangible asset has been created. the newly developed product is brought to market in january 2018 and is expected to generate sales revenue for 10 years. assume that a u.s.–based company is issuing securities to foreign investors who require financial statements prepared in accordance with ifrs. thus, adjustments to convert from u.s. gaap to ifrs must be made. ignore income taxes. required: (a) prepare journal entries for research and development costs for the years ending december 31, 2017, and december 31, 2018, under (1) u.s. gaap and (2) ifrs. (c) prepare the entry(ies) that trecek would make on the december 31, 2017, and december 31, 2018, conversion worksheets to convert u.s. gaap balances to ifrs.
Answers: 1
question
Business, 22.06.2019 15:10
Paying attention to the purpose of her speech, which questions can she eliminate? a. 1 and 2 b. 3 c. 2 and 4 d. 1-4
Answers: 2
You know the right answer?
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine....
Questions
question
Mathematics, 12.09.2019 10:10
question
Mathematics, 12.09.2019 10:10
question
Biology, 12.09.2019 10:10
Questions on the website: 13722363