Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that even though we should have approximately 83 percent (or more precisely 25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project. Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance $ Schedule performance index Cost variance $ Cost performance index

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 16:10
Belstone, inc. is a merchandiser of stone ornaments. it sold 15,000 units during the year. the company has provided the following information: sales revenue $ 520,000 purchases (excluding freight in) 338,500 selling and administrative expenses 32,000 freight in 15,000 beginning merchandise inventory 43,000 ending merchandise inventory 58,500 how much is the gross profit for the year?
Answers: 3
question
Business, 22.06.2019 00:00
If his parents cannot alex with college, and two of his scholarships will be awarded to other students if he does not accept them immediately, which is the best option for him?
Answers: 1
question
Business, 22.06.2019 19:00
12. to produce a textured purée, you would use a/an a. food processor. b. wide-mesh sieve. c. immersion blender d. food mill.
Answers: 1
question
Business, 22.06.2019 20:00
In william rathje's garbology project that focused on household waste, front door interviews found 15 percent of respondents saying that they consumed beer. the trash discard from the same area showed what percentage of household's consuming beer
Answers: 1
You know the right answer?
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The projec...
Questions
Questions on the website: 13722363