Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

Activity/Time(weeks)

A:6weeks
B:7 weeks
C:3weeks
D:2weeks
E:4weeks
F:6weeks
G:10weeks
H:7weeks

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 01:50
Which value describes the desire to be one’s own boss? a. autonomy b. status c. security d. entrepreneurship
Answers: 2
question
Business, 22.06.2019 08:00
Why is it vital to maintain a designer worksheet? a. it separates the designs chosen for the season from those rejected by the company. b. it keeps a record of all designs created by the designer for a season. c. it charts out the development of an entire line through the season and beyond. d. it tracks the development of a design along with costing and production details. done
Answers: 1
question
Business, 22.06.2019 12:10
Lambert manufacturing has $100,000 to invest in either project a or project b. the following data are available on these projects (ignore income taxes.): project a project b cost of equipment needed now $100,000 $60,000 working capital investment needed now - $40,000 annual cash operating inflows $40,000 $35,000 salvage value of equipment in 6 years $10,000 - both projects will have a useful life of 6 years and the total cost approach to net present value analysis. at the end of 6 years, the working capital investment will be released for use elsewhere. lambert's required rate of return is 14%. the net present value of project b is:
Answers: 2
question
Business, 22.06.2019 18:30
Health insurance protects you if you experience any of the following except: a: if you have to be hospitalized b: if you damage someone's property c: if you need to visit a clinic d: if you can't work because of illness
Answers: 2
You know the right answer?
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine....
Questions
question
Mathematics, 23.04.2021 02:20
question
Mathematics, 23.04.2021 02:20
question
Mathematics, 23.04.2021 02:20
question
Mathematics, 23.04.2021 02:20
Questions on the website: 13722363