Schedule compression

i. what is the crash cost per day for each activity?
ii. which activities should be crashed to meet a project deadline of 10 days with a minimum cost? you may assume that you can partially crash an activity.
iii. what is the new cost after crashing the project?
iv. is partial crashing an appropriate assumption for this kind of project?

activity

normal time

crash time

normal cost

crash cost

a

7

4

$500

$800

b

3

2

$200

$350

c

6

4

$500

$900

d

5

1

$200

$500

e

2

1

$300

$550

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 16:10
Computing depreciation, net book value, and gain or loss on asset sale lynch company owns and operates a delivery van that originally cost $46,400. lynch has recorded straight-line depreciation on the van for four years, calculated assuming a $5,000 expected salvage value at the end of its estimated six-year useful life. depreciation was last recorded at the end of the fourth year, at which time lynch disposes of this van. compute the net bookvalue of the van on the disposal date.
Answers: 1
question
Business, 22.06.2019 16:30
Suppose that electricity producers create a negative externality equal to $5 per unit. further suppose that the government imposes a $5 per-unit tax on the producers. what is the relationship between the after-tax equilibrium quantity and the socially optimal quantity of electricity to be produced?
Answers: 2
question
Business, 22.06.2019 22:50
What is one of the advantages of getting a government-sponsored mortgage instead of a conventional mortgage
Answers: 1
question
Business, 23.06.2019 00:50
Hubert manages a grocery store in a country experiencing a high rate of inflation. to keep up with inflation, he spends a lot of time every day updating the prices, printing new price tags, and sending out newspaper inserts advertising the new prices. his employees regularly deal with customer annoyance over the frequent price changes. this is an example of the of inflation.
Answers: 2
You know the right answer?
Schedule compression

i. what is the crash cost per day for each activity?
ii. w...
Questions
question
Mathematics, 30.09.2021 21:50
Questions on the website: 13722367