If it takes a supplier 25 days to deliver an order once it has been placed and the standard deviation of daily demand is 20, which of the following is the standard deviation of usage during lead time?
a. 50
b. 100
c. 400
d. 1,000
e. 1,600

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 18:50
You are the manager of a firm that produces output in two plants. the demand for your firm's product is p = 20 − q, where q = q1 + q2. the marginal costs associated with producing in the two plants are mc1 = 2 and mc2 = 2q2. how much output should be produced in plant 1 in order to maximize profits?
Answers: 3
question
Business, 21.06.2019 23:00
The company financial officer was interested in the average cost of pcs that had been purchased in the past six months. she took a random sample of the price of 10 computers, with the following results. $3,250, $1,127, $2,995, $3,250, $3,445, $3,449, $1,482, $6,120, $3,009, $4,000 what is the iqr?
Answers: 2
question
Business, 22.06.2019 15:30
Uknow what i love about i ask a dumb question it is immediately answered but when i ask a real question it take like an hour to get answered
Answers: 2
question
Business, 22.06.2019 19:50
The new york company produces high quality chairs. variable manufacturing overhead is applied at a standard rate of $12 per machine hour. each chair requires a standard quantity of six machine hours. production for the month totaled 4,000 units. calculate: the standard cost per unit for variable overhead. select one: a. $130,000 b. $192,000 c. $90,000 d. $100,000
Answers: 2
You know the right answer?
If it takes a supplier 25 days to deliver an order once it has been placed and the standard deviatio...
Questions
question
Biology, 19.10.2020 22:01
question
Mathematics, 19.10.2020 22:01
question
Mathematics, 19.10.2020 22:01
question
Mathematics, 19.10.2020 22:01
Questions on the website: 13722363