Reep construction recently won a contract for the excavation and site preparation of a new rest area on the pennsylvania turnpike. in preparing his bid for the job, bob reep, founder and president of reep construction, estimated that it would take four months to perform the work and that 10, 12, 14, and 8 trucks would be needed in months 1 through 4, respectively.

the firm currently has 20 trucks of the type needed to perform the work on the new project. these trucks were obtained last year when bob signed a long-term lease with pennstate leasing. although most of these trucks are currently being used on existing jobs, bob estimates that one truck will be available for use on the new project in month 1, two trucks will be available in month 2, three trucks will be available in month 3, and one truck will be available in month 4. thus, to complete the project, bob will have to lease additional trucks.

the long-term leasing contract with pennstate charges a monthly cost of $600 per truck. reep construction pays its truck drivers $20 an hour, and daily fuel costs are approximately $100 per truck. all maintenance costs are paid by pennstate leasing. for planning purposes, bob estimates that each truck used on the new project will be operating eight hours a day, five days a week for approximately four weeks each month.

bob does not believe that current business conditions justify committing the firm to ad- ditional long-term leases. in discussing the short-term leasing possibilities with pennstate leasing, bob learned that he can obtain short-term leases of one to four months. short-term leases differ from long-term leases in that the short-term leasing plans include the cost of both a truck and a driver. maintenance costs for short-term leases also are paid by pennstate leas- ing. the following costs for each of the four months cover the lease of a truck and driver:

col1 length of lease 1 2 3 4
col2 cost per month $ 4000 $ 3700 $3225 $ 3040

bob reep would like to acquire a lease that minimizes the cost of meeting the monthly trucking requirements for his new project, but he also takes great pride in the fact that his company has never laid off employees. bob is committed to maintaining his no-layoff policy; that is, he will use his own drivers even if costs are higher. managerial report perform an analysis of reep construction%u2019s leasing problem and prepare a report for bob reep that summarizes your findings. be sure to include information on and analysis of the following items: 1. the optimal leasing plan2. the costs associated with the optimal leasing plan3. the cost for reep construction to maintain its current policy of no layoffs

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 13:40
Jung hwa was recently married on july 1, 2018. she had worked for the organization for the past eight years and has been covered under its group healthcare insurance policy during the entire period. when can jung hwa add her new spouse to her insurance plan?
Answers: 1
question
Business, 22.06.2019 12:50
Afirm’s production function is represented by q(m,r) = 4m 3/4r1/3, where q denotes output, m raw materials, and r robots. the firm is currently using 6 units of raw materials and 12 robots. according to the mrts, in order to maintain its output level the firm would need to give up 2 robots if it adds 9 units of raw materials. (a) true (b) false
Answers: 3
question
Business, 22.06.2019 14:50
Pear co.’s income statement for the year ended december 31, as prepared by pear’s controller, reported income before taxes of $125,000. the auditor questioned the following amounts that had been included in income before taxes: equity in earnings of cinn co. $ 40,000 dividends received from cinn 8,000 adjustments to profits of prior years for arithmetical errors in depreciation (35,000) pear owns 40% of cinn’s common stock, and no acquisition differentials are relevant. pear’s december 31 income statement should report income before taxes of
Answers: 3
question
Business, 22.06.2019 21:20
1. what are the unique operational challenges to delivering fresh meals? 2. why is speed of delivery so important for delivered meals? what variety of options contribute to this performance metric? 3. how could operations management concepts be utilized to improve the performance of freshly? 4. what are your typical product delivery times? what would be required to speed these up? 5. what are your delivery batch quantities? how could you reduce batch size and reduce delivery cost simultaneously using operations management concepts?
Answers: 2
You know the right answer?
Reep construction recently won a contract for the excavation and site preparation of a new rest area...
Questions
question
Chemistry, 20.11.2020 05:20
question
History, 20.11.2020 05:30
question
Mathematics, 20.11.2020 05:30
question
Chemistry, 20.11.2020 05:30
question
Mathematics, 20.11.2020 05:30
Questions on the website: 13722367