The flapjack corporation had 8,200 actual direct labor hours at an actual rate of $12.40 per hour. original

production had been budgeted for 1,100 units, but only 1,000 units were actually produced. labor

standards were 7.6 hours per completed unit at a standard rate of $13.00 per hour.

compute the labor time variance.:

a: 9,880f

b: 9,880u

c: 7,800u

d: 7,800f

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 12:10
Gwen, a manager at exude apparels inc., received a message from a customer requesting a replacement for a purchased pair of shoes. exude apparels has a clearly stated no-return policy. gwen responded to the customer denying the request in a tactful and clear manner. despite this, the customer submitted a second request. in this scenario, which of the following is an appropriate response to the second request?
Answers: 2
question
Business, 22.06.2019 13:30
Presented below is information for annie company for the month of march 2018. cost of goods sold $245,000 rent expense $ 36,000 freight-out 7,000 sales discounts 8,000 insurance expense 5,000 sales returns and allowances 11,000 salaries and wages expense 63,000 sales revenue 410,000 instructions prepare the income statement.
Answers: 2
question
Business, 22.06.2019 17:40
Solomon chemical company makes three products, b7, k6, and x9, which are joint products from the same materials. in a standard batch of 320,000 pounds of raw materials, the company generates 70,000 pounds of b7, 150,000 pounds of k6, and 100,000 pounds of x9. a standard batch costs $3,840,000 to produce. the sales prices per pound are $10, $14, and $20 for b7, k6, and x9, respectively. (a) allocate the joint product cost among the three final products using weight as the allocation base. (b) allocate the joint product cost among the three final products using market value as the allocation base. (c) allocate the joint product cost among the three final products using weight as the allocation base.
Answers: 3
question
Business, 22.06.2019 18:50
Plastic and steel are substitutes in the production of body panels for certain automobiles. if the price of plastic increases, with other things remaining the same, we would expect: a) the demand curve for plastic to shift to the left. b) the price of steel to fall. c) the demand curve for steel to shift to the left d) nothing to happen to steel because it is only a substitute for plastic. e) the demand curve for steel to shift to the right
Answers: 3
You know the right answer?
The flapjack corporation had 8,200 actual direct labor hours at an actual rate of $12.40 per hour. o...
Questions
question
Advanced Placement (AP), 03.08.2019 13:00
Questions on the website: 13722359