There are many causes of variation in project costs. which of the following accurately describes the nature of this variation?
a. normal cause variation is when something out of the ordinary occurs.
b. variation occurs in all work processes and the novelty associated with most projects creates many opportunities for variation.
c. special cause variation comes from many small causes that are inherent in a work process.
d. variation is generally greater on projects that use well-known technology and an experienced project team.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 21:20
Trinity coatings company uses the indirect method to prepare its statement of cash flows. refer to the following information for 2018: the beginning balance in the cash account was $ 3 comma 000. net cash provided by operating activities: $ 42 comma 000 net cash used for investing activities: $(26 comma 500) net cash provided by financing activities: $ 1 comma 700 the statement of cash flows will show
Answers: 2
question
Business, 22.06.2019 01:20
Which of the following statements concerning an organization's strategy is true? a. cost accountants formulate strategy in an organization since they have more inputs about costs. b. businesses usually follow one of two broad strategies: offering a quality product at a high price, or offering a unique product or service priced lower than the competition. c. a good strategy will always overcome poor implementation. d. strategy specifies how an organization matches its own capabilities with the opportunities in the marketplace to accomplish its objectives.
Answers: 1
question
Business, 22.06.2019 03:20
The treasurer for pittsburgh iron works wishes to use financial futures to hedge her interest rate exposure. she will sell five treasury futures contracts at $139,000 per contract. it is july and the contracts must be closed out in december of this year. long-term interest rates are currently 7.30 percent. if they increase to 9.50 percent, assume the value of the contracts will go down by 20 percent. also if interest rates do increase by 2.2 percent, assume the firm will have additional interest expense on its business loans and other commitments of $149,000. this expense, of course, will be separate from the futures contracts. a. what will be the profit or loss on the futures contract if interest rates increase to 9.50 percent by december when the contract is closed out
Answers: 1
question
Business, 22.06.2019 07:50
The questions of economics address which of the following ? check all that apply
Answers: 3
You know the right answer?
There are many causes of variation in project costs. which of the following accurately describes the...
Questions
question
Mathematics, 13.06.2020 03:57
Questions on the website: 13722363