Under a contract with valley vineyard, walsh begins grading a terraced hillside for the planting of grapes. halfway through the project, walsh asks for $5,000 over the contract price, claiming an increase in the "cost of doing business."

valley agrees but later refuses to pay. valley's agreement to pay more is :

a. unenforceable because walsh's performance was a preexisting duty.

b. unenforceable because valley's promise was illusory.

c. enforceable.

d. unenforceable because walsh's request modified the contract.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 17:30
An essential element of being receptive to messages is to have an open mind true or false
Answers: 2
question
Business, 22.06.2019 17:30
Four students are at an extracurricular activity fair at their high school and are trying to decide which clubs to join. some information about the students is listed in this chart: which describes which ctso each student should join?
Answers: 1
question
Business, 22.06.2019 22:20
With q7 assume the sweet company uses a plantwide predetermined overhead rate with machine-hours as the allocation base.and for q 10,11,13,and 14,assume that the company use department predetermined overhead rates with machine-hours as the allocation bade in both departements.7. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answers to nearest whole dollar.)total price for the job for job p -job q selling price per unit for job p q . how much manufacturing overhead was applied from the molding department to job p and how much was applied to job q? (do not round intermediate calculations.) job p job q manufacturing overhead applied for job p for job q . how much manufacturing overhead was applied from the fabrication department to job p and how much was applied to job q? (do not round intermediate calculations.)job p job q manufacturing overhead applied for job p for job q . if job q included 30 units, what was its unit product cost? (do not round intermediate calculations. round your final answer to nearest whole dollar.)14. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answer to nearest whole dollar.)total price for the job p for job q selling price per unit for job p for job q
Answers: 1
question
Business, 22.06.2019 22:20
What type of negotiating strategy requires the supplier to open its books to the purchasers? a. competitive biddingb. cost-based price modelc. price-based modeld. market-based price modele. transparent negotiations
Answers: 1
You know the right answer?
Under a contract with valley vineyard, walsh begins grading a terraced hillside for the planting of...
Questions
question
Mathematics, 02.04.2021 16:20
question
Biology, 02.04.2021 16:20
question
Mathematics, 02.04.2021 16:20
Questions on the website: 13722363