The demand for subassembly s is 100 units in week 7. each unit of s requires 1 unit of t and 2 units of u. each unit of t requires 1 unit of v, 2 units of w, and 1 unit of x. finally, each unit of u requires 2 units of y and 3 units of z. one firm manufactures all items. it takes 2 weeks to make s, 1 week to make t, 2 weeks to make u, 2 weeks to make v, 3 weeks to make w, 1 week to make x, 2 weeks to make y, and 1 week to make z.

a) construct a product structure. identify all levels, parents, and components.
b) prepare a time-phased product structure.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 08:10
The last time he flew jet value air, juan's plane developed a fuel leak and had to make an 4) emergency landing. the time before that, his plane was grounded because of an electrical problem. juan is sure his current trip will be fraught with problems and he will once again be delayed. this is an example of the bias a) confirmation b) availability c) selective perception d) randomness
Answers: 1
question
Business, 22.06.2019 11:20
Camilo is a self-employed roofer. he reported a profit of $30,000 on his schedule c. he had other taxable income of $5,000. he paid $3,000 for hospitalization insurance. his self-employment tax was $4,656. he paid his former wife $4,000 in court-ordered alimony and $4,000 in child support. what is the amount camilo can deduct in arriving at adjusted gross income (agi)?
Answers: 2
question
Business, 22.06.2019 20:40
Robert owns a life insurance policy that he purchased when he first graduated college. it has a $100,000 death benefit and robert pays premiums for it every month out of his checking account. the insurance robert has is most likely da. permanent life insurance o b. term life insurance o c. group life insurance o d. individual life insurance
Answers: 1
question
Business, 22.06.2019 22:00
The company is experiencing an increase in competition, and at the same time they are building more production facilities in southeast asia. in this scenario, the top management team is most likely to multiple choice increase the cost of their products. restructure to reflect a more bureaucratic, stable organization. pull decision-making responsibility from low-level management, taking it on themselves. give lower-level managers the authority to make decisions to benefit the firm. rid themselves of all buffering product.
Answers: 3
You know the right answer?
The demand for subassembly s is 100 units in week 7. each unit of s requires 1 unit of t and 2 units...
Questions
question
Mathematics, 12.05.2021 01:00
question
Mathematics, 12.05.2021 01:00
question
Social Studies, 12.05.2021 01:00
Questions on the website: 13722361