When it is necessary to reduce project duration and resources are constrained, which of the following is not a reasonable option?
select one:
a. compromise quality
b. establishing a core project team
c. reduce project scope
d. fast-tracking
e. critical-chain project management

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:00
In order to minimize project risk which step comes after the step of identifying risks
Answers: 1
question
Business, 22.06.2019 03:20
Yael decides that she no longer enjoys her job, and she quits to open a gluten-free, dairy-free kosher bakery. she pays a monthly rent for her store of $2,000. her labor costs for one month are $4,500, and she spends $6,000 a month on nut flours, sugar, and other supplies. yael was earning $2,500 a month working as a bank teller. these are her only costs. her monthly revenue is $14,000. which of the following statements about yaelโ€™s costs and profit are correct? correct answer(s) an accountant would say she is earning a monthly profit of $1,500. her implicit costs are $2,500 a month. an economist would tell her that she is experiencing a loss. her total costs are $12,500 a month. her explicit costs include the labor, rent, and supplies for her store. her economic profit is $1,500 a month.
Answers: 3
question
Business, 22.06.2019 16:10
From what part of income should someone take savings?
Answers: 2
question
Business, 22.06.2019 17:30
What is one counter argument to the premise that the wealth gap is a serious problem which needs to be addressed?
Answers: 1
You know the right answer?
When it is necessary to reduce project duration and resources are constrained, which of the followin...
Questions
question
Computers and Technology, 28.12.2020 14:00
question
English, 28.12.2020 14:00
question
Mathematics, 28.12.2020 14:00
question
Social Studies, 28.12.2020 14:00
Questions on the website: 13722362