subject
Business, 08.11.2019 21:31 DiegoMath

The northeast independent school district in bexar county, texas, hired str constructors, ltd., to renovate a middle school. str subcontracted the tile work in the school's kitchen to newman tile, inc. (nti). the project had already fallen behind schedule. as a result, str allowed other workers to walk over and damage the newly installed tile before it had cured, forcing nti to constantly redo its work. despite nti's requests for payment, str remitted only half the amount due under their contract. when the school district refused to accept the kitchen, including the tile work, str told nti to quickly make the repairs. a week later, str terminated their contract. upon entering a contract, parties obtain both1. select: powers, money, rights, status, offers, or acceptances 2. select: duties, powers, money, status, offers, or acceptancesif a party enters a contract, what is the most common way for that party to discharge its duties under the contract? 3. select: file a lawsuit against the other party for nonperformance, perform the contractual duty, pay a portion and then file a lawsuit against the other party for nonperformance, or perform the duty as much as possible in the time frame allota breach of contract occurs when there is nonperformance of a contractual duty? 4. select: yes or noif the performance is substantial, but not complete, is there a breach? 5. select: yes or nowhat type of breach? 6. select: material or minorif the performance is less than substantial is there a breach? 7. select: yes or nowhat type of breach? 8. select: material or minorif the breach of one party is material (they have less than substantially performed) is the other party discharged from performing their duties under the contract? 9. select: yes or noif the breach of one party is minor (they have substantially or completely performed) is the other party discharged from performing their duties under the contract? 10.select: yes or noin any type of breach, is the non-breaching party entitled to sue for damages? 11. select: yes or nohow many contracts are there? 12. select: one, two, three, or fourwho did newman contract with? 13. select: str, northeast, or both str and northeastwhat was newman's primary duty under the contract? 14. select: to tile the school's cafeteria or to repair the tile workwhat was str's duty under the contract? 15. select: to allow newman to complete the worktake over the tile work if newman couldn't complete it, pay newman half of the contract amount if the tile work was not completed on time, bring in other workers to trample newman's tiles, or pay newman only if the tile work met str's satisfaction16. select: pay newman for the tile worktake over the tile work if newman couldn't complete it, pay newman half of the contract amount if the tile work was not completed on time, bring in other workers to trample newman's tiles, or pay newman only if the tile work met str's satisfactionwhich party failed to perform its part of the contract? 17. select: str or newmanin what ways did str fail to perform its duties under the contract? 18. select: nti had to redo its work constantly because str permitted others to walk over and damage the newly installed tile, str didn't give notice to nti about its intention not to pay, str failed to put a condition in the contract, or nti needed to do more to protect its work area19. select: despite nti's requests for payment, str remitted only half the amount due under their contract, str didn't give notice to nti about its intention not to pay, str failed to put a condition in the contract, or nti needed to do more to protect its work areaitem20. select: str terminated the contract, apparently wrongfully and without cause, str didn't give notice to nti about its intention not to pay, str failed to put a condition in the contract, or nti needed to do more to protect its work areaitem 20str's performance of duties under the contract was? 21. select: substantial or less than substantialitemdid str breach the contract? 22. select: yesor nowas the breach minor or material? 23. select: minor or materialwere newman's duties under the contract discharged? 24. select: yes or nowhat does this mean? 25. select: newman no longer needed to perform under the contract or newman needed to fix the tiles for the school districtcan newman sue for damages? 26. select: yes or nois a court likely to find for newman? 27. select: yes or nowhat if the tile work had proceeded as contracted and looked good but str refused to pay saying it didn't meet their personal satisfaction even though the contract didn't mention this - could str refuse to pay? 28. select: yes or nowhose standard must the work meet? 29. select: str, newman, school district, or reasonable person

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
The link between volume of production and the cost of building manufacturing operations is particularly important in industries characterized byanswers: process innovations.product manufacturing.product innovation.process manufacturing.
Answers: 1
question
Business, 21.06.2019 22:30
True or false: banks are required to make electronically deposited funds available on the same day of the deposit
Answers: 2
question
Business, 22.06.2019 02:30
rural residential development company and suburban real estate corporation form a joint stock company. the longest duration a joint stock company can be formed for is
Answers: 2
question
Business, 22.06.2019 07:30
1  2  3  4  5  6  7  8  9  10time remaining59: 30in  the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war? 1 2 3 4 5 6 7 8 9 10time remaining59: 30in the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war?
Answers: 1
You know the right answer?
The northeast independent school district in bexar county, texas, hired str constructors, ltd., to r...
Questions
question
Mathematics, 04.11.2019 18:31
Questions on the website: 13722362