Acertain project has three activities on its critical path. activity a’s normal completion time is five days. it can be crashed to three days at a cost of $500. activity b’s normal completion time is six days, and it can be crashed to four days at a cost of $50. activity c’s normal completion time is eight days. it can be crashed to three days at a cost of $1,000. which activity should the project manager crash first, by how many days, and how much will it cost?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 13:30
List five words to describe your dominant culture. list five words to describe a culture with which you are not a member, have little or no contact, or have limited knowledge. can someone give me a example on how to answer this?
Answers: 1
question
Business, 21.06.2019 20:50
What is the best definition of a conclusion?
Answers: 1
question
Business, 22.06.2019 23:30
Sally mitchell works as a manager at an environmental organization. she is currently working on a global warming project and decides which tasks related to creating awareness about the issue need to be done. in addition, she is also deciding which members of her team will work on engaging with the public and which will work on lobbying with the government. she is also assigning people as team members to ensure that tasks are undertaken on time. which of the following categories of functions is mitchell undertaking? envisioning organizing controlling planning
Answers: 1
question
Business, 23.06.2019 00:10
Mno corporation uses a job-order costing system with a predetermined overhead rate based on direct labor-hours. the company based its predetermined overhead rate for the current year on the following data: total estimated direct labor-hours 50,000 total estimated fixed manufacturing overhead cost $ 285,000 estimated variable manufacturing overhead per direct labor-hour $ 3.80 recently, job p123 was completed with the following characteristics: total actual direct labor-hours 20 direct materials $ 710 direct labor cost $ 500 the amount of overhead applied to job p123 is closest to:
Answers: 2
You know the right answer?
Acertain project has three activities on its critical path. activity a’s normal completion time is f...
Questions
question
Computers and Technology, 08.11.2020 02:50
question
Mathematics, 08.11.2020 02:50
Questions on the website: 13722363