Your project to obtain charitable donations is now 36 days into a planned 46-day project. the project is divided into 3 activities. the first activity is designed to solicit individual donations. it is scheduled to run the first 31 days of the project and to bring in $25,100. even though we are 36 days into the project, we still see that we have only 90% of this activity complete. the second activity relates to company donations and is scheduled to run for 36 days starting on day 5 and extending through day 41. we estimate that even though we should have (31/36) 86% of this activity complete, it is actually only 58% complete. this part of the project was scheduled to bring in $150,100 in donations. the final activity is for matching funds. this activity is scheduled to run the last 10 days of the project and has not started. it is scheduled to bring in an additional $50,200. so far $175,600 has actually been brought in on the project. calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (negative values should be indicated by a minus sign. do not round intermediate calculations. round your dollar amounts to the nearest whole number. round your "performance index" values to 3 decimal places.) schedule variance $ schedule performance index cost variance $ cost performance index

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 00:00
Pettijohn inc. the balance sheet and income statement shown below are for pettijohn inc. note that the firm has no amortization charges, it does not lease any assets, none of its debt must be retired during the next 5 years, and the notes payable will be rolled over. balance sheet (millions of $) assets 2016 cash and securities $ 1,554.0 accounts receivable 9,660.0 inventories 13,440.0 total current assets $24,654.0 net plant and equipment 17,346.0 total assets $42,000.0 liabilities and equity accounts payable $ 7,980.0 notes payable 5,880.0 accruals 4,620.0 total current liabilities $18,480.0 long-term bonds 10,920.0 total debt $29,400.0 common stock 3,360.0 retained earnings 9,240.0 total common equity $12,600.0 total liabilities and equity $42,000.0 income statement (millions of $) 2016 net sales $58,800.0 operating costs except depr'n $54,978.0 depreciation $ 1,029.0 earnings bef int and taxes (ebit) $ 2,793.0 less interest 1,050.0 earnings before taxes (ebt) $ 1,743.0 taxes $ 610.1 net income $ 1,133.0 other data: shares outstanding (millions) 175.00 common dividends $ 509.83 int rate on notes payable 1. what is the firm's current ratio? (points : 6) 0.97 1.08 1.20 1.33 2. what is the firm's quick ratio? (points : 6) 0.49 0.61 0.73 0.87 3. what is the firm's total assets turnover? (points : 6) 0.90 1.12 1.40 1.68 4. what is the firm's inventory turnover ratio? (points : 6) 4.38 4.59 4.82 5.06 5. what is the firm's debt ratio? (points : 6) 45.93% 51.03% 56.70% 70.00% 6. what is the firm's roa? (points : 6) 2.70% 2.97% 3.26% 3.59% 7. what is the firm's roe? (points : 6) 8.54% 8.99% 9.44% 9.91%
Answers: 2
question
Business, 22.06.2019 14:20
Your uncle borrows $53,000 from the bank at 11 percent interest over the nine-year life of the loan. use appendix d for an approximate answer but calculate your final answer using the formula and financial calculator methods. what equal annual payments must be made to discharge the loan, plus pay the bank its required rate of interest
Answers: 1
question
Business, 22.06.2019 15:30
The school cafeteria can make pizza for approximately $0.30 a slice. the cost of kitchen use and cafeteria staff runs about $200 per day. the pizza den nearby will deliver whole pizzas for $9.00 each. the cafeteria staff cuts the pizza into eight slices and serves them in the usual cafeteria line. with no cooking duties, the staff can be reduced by half, for a fixed cost of $75 per day. should the school cafeteria make or buy its pizzas?
Answers: 3
question
Business, 22.06.2019 16:00
In macroeconomics, to study the aggregate means to study blank
Answers: 1
You know the right answer?
Your project to obtain charitable donations is now 36 days into a planned 46-day project. the projec...
Questions
question
Mathematics, 05.09.2021 03:30
question
Mathematics, 05.09.2021 03:30
question
English, 05.09.2021 03:30
question
Chemistry, 05.09.2021 03:40
question
Computers and Technology, 05.09.2021 03:40
question
Chemistry, 05.09.2021 03:40
Questions on the website: 13722363