Which of the following steps is not a basic step followed by pert and cpm?
a. compute the critical path.
b. draw the network connecting all the activities.
c. define the project.
d. identify and eliminate non-critical activities.

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 18:20
Which of the following accurately describes a situation in which consumers have elastic demand? a. a restaurant starts using margarine instead of butter because butter becomes more expensive. b. consumers boycott a restaurant because the waiters aren't paid minimum wage. c. a company starts using sugar instead of corn syrup because its revenues are up. d. people give up eating pasta and bread because they want to lose weight. 2b2t
Answers: 1
question
Business, 22.06.2019 13:40
Computing equivalent units is especially important for: (a) goods that take a relatively short time to produce, such as plastic bottles. (b) goods with sustainability implications in their production processes. (c) goods that are started and completed during the same period. (d) goods that take a long time to produce, such as airplanes.
Answers: 2
question
Business, 22.06.2019 20:20
Xinhong company is considering replacing one of its manufacturing machines. the machine has a book value of $39,000 and a remaining useful life of 5 years, at which time its salvage value will be zero. it has a current market value of $49,000. variable manufacturing costs are $33,300 per year for this machine. information on two alternative replacement machines follows. alternative a alternative b cost $ 115,000 $ 117,000 variable manufacturing costs per year 22,900 10,100 1. calculate the total change in net income if alternative a and b is adopted. 2. should xinhong keep or replace its manufacturing machine
Answers: 1
question
Business, 22.06.2019 20:30
The research of robert siegler and eric jenkins on the development of the counting-on strategy is an example of design.
Answers: 3
You know the right answer?
Which of the following steps is not a basic step followed by pert and cpm?
a. compute the cr...
Questions
question
Mathematics, 28.04.2021 06:30
question
Mathematics, 28.04.2021 06:30
question
English, 28.04.2021 06:30
question
Biology, 28.04.2021 06:30
question
Mathematics, 28.04.2021 06:30
question
History, 28.04.2021 06:30
Questions on the website: 13722363